Development in unincorporated Lake County runs through the Planning, Building and Development Department, and the county has built a formal front door for it. The Early Assistance process exists to put a project in front of every reviewing department before plans are drawn, and for nonresidential projects it takes the form of a coordinated meeting.

Although skipping it is possible in some instances, the early assistance process can be helpful because the project team may discover a floodplain constraint, a woodland protection requirement, or a site capacity limit early on and avoid exceeding the design budget and costly delays.

What Is an Early Assistance Meeting?

Early Assistance is the county’s pre-application process for projects in unincorporated Lake County. Its stated purpose is to save applicant time and effort through coordinated and timely county guidance.

The county splits the process by project type:

  • Early Assistance letters apply to residential projects, excluding residential subdivisions. These letters identify project requirements and design issues before work begins, and are provided at no charge.
  • Early Assistance meetings apply to nonresidential projects. A project manager coordinates the meeting and ensures all applicable county departments are present to evaluate the proposal against county regulations.

For commercial, industrial, and mixed-use development, the meeting is the relevant path. Notes from the meeting are provided to the applicant afterward, which creates a written record of what the county identified.

Who Should Request One, and When?

The county describes the process as most effective when an applicant has a defined objective, a vision paired with a specific site, and either ownership of the land or the owner’s permission to use it.

That last condition deserves attention from anyone evaluating a site under contract. A prospective buyer without the owner’s permission is not positioned to use the process well, which argues for addressing county access during due diligence rather than after closing.

Early Assistance can begin in two ways:

  • The applicant requests it before applying for a permit.
  • A project manager determines during discussions that the project warrants an Early Assistance letter or meeting.

Requests are made by contacting a project manager at the department directly. The permits and Early Assistance page sets out the process and the department’s contact information.

What the Meeting Actually Delivers

The value is coordination. Rather than sequential feedback from separate divisions over months, the applicant gets the reviewing departments in one place. Practical outputs include:

  • Identification of solutions to challenges on a complicated site.
  • Answers on how county regulations apply to the specific proposal.
  • Referrals to consultants who can assist with design, where the county is able to help.
  • Written meeting notes for use in design and layout.

The departments in the room typically include zoning, stormwater and land development, floodplain and wetlands review, and building, depending on the project. For sites with a septic system or private well, the Lake County Health Department review runs in parallel.

When Early Assistance Is Effectively Mandatory

For some approvals, the county requires the meeting rather than offering it. Two examples matter for commercial development:

  • Commercial solar energy systems. Applicants are required to attend an Early Assistance meeting before preparing a conditional use permit application.
  • Use permits for commercial projects. The department directs applicants to speak with a project manager, who schedules a meeting with the staff who will conduct the review.

Even where it is optional, the county’s own guidance on variations recommends a meeting before preparing an application. The pattern is consistent: the county treats Early Assistance as the mechanism for surfacing problems while they are still easy to solve.

What to Submit to Get Value From the Meeting

A meeting is only as useful as the information available in it. Productive sessions generally involve:

  • A plat of survey showing legal boundaries and the area of the property.
  • The property index number or address for the site.
  • A narrative describing the proposed use, the square footage dedicated to each use, and anticipated employee counts.
  • A conceptual site layout, including building footprints, parking, and any anticipated stormwater detention.
  • Known information on natural resources present on the property.
  • Specific questions on the constraints most likely to drive the design.

Arriving with a concept rather than a finished design is the point. The meeting is intended to shape a plan, not to review one that has already been engineered.

How Early Assistance Fits the Broader Approval Path

Early Assistance is a starting point, not an approval. The permits and approvals that may follow include:

  • Building permits for new construction, additions, and alterations.
  • Change of use permits when the use of land or a building changes.
  • Site development permits for grading, filling, or moving earth.
  • Conditional use permits to establish certain uses.
  • Zoning approvals, including rezonings and variations.
  • Subdivision approvals where land is being divided.

Applications are submitted in person by the property owner or an authorized agent, and the owner’s signature is required on the application form for use permits. Identifying which of these a project needs is one of the more valuable outputs of an early meeting, because each carries its own timeline.

Making the Early Assistance Meeting Count

The strategic case for Early Assistance is sequencing. County review in unincorporated Lake County layers zoning, site capacity, natural resource protection, and stormwater requirements, and those constraints interact. Learning about them together, before design commitments, is materially cheaper than learning about them one denial at a time.

A short approach for any development team entering the county:

  • Request the meeting during due diligence rather than after site control.
  • Confirm the parcel is unincorporated, since property inside a municipality follows that municipality’s rules.
  • Treat the written meeting notes as a design brief and a record.
  • Map the approvals identified in the meeting against the project schedule before committing to a closing date.

Birchwood Law advises developers, investors, and business owners on land use and zoning approvals in Lake County, including pre-application strategy and hearings before the Zoning Board of Appeals. To discuss a project in unincorporated Lake County, contact Birchwood Law.

This article is for general information and does not constitute legal advice. Requirements depend on the specific property and current code provisions.

Author Bio

Harrison Bodourian, Esq. - Founding Attorney

Katarina Karac
Katarina is a Chicagoland zoning attorney with a deep understanding of how planning staff and local officials approach land use decisions, thanks to her prior work representing public development agencies. She now uses that experience to help private clients move projects through the approval process with focus and efficiency.

She has guided residential, commercial, mixed-use, and industrial developments from concept to approval, appearing before boards, commissions, and neighborhood groups. Known for her clear communication and high success rate, Katarina also regularly presents on zoning and land use at legal seminars and CLEs.